[D8439ZAJ1], Memorandum, Edison (Thomas A.) Construction Dept, March 11th, 1884

https://edisondigital.rutgers.edu/document/D8439ZAJ1

View document with UniversalViewer   → View document on Archive.org  → Re-use this digital object via a IIIF manifest

Title

[D8439ZAJ1], Memorandum, Edison (Thomas A.) Construction Dept, March 11th, 1884

Editor's Notes

Specifics about removing obstructions and allaying public concern when setting up stations and grids. Responsibility of contractors for removing obstructions. Suggests revised payment sked: 1st 30% at signing of contract. 2nd 35% when street installation done. 3rd 25% when plant goes live. 4th 10% after 30 days operation.

Mentioned